CAPITAL METRORAIL PROGRESS REPORT – JUNE 19, 2009
Capital Metro has made significant progress on the MetroRail project since last month’s report. We are much closer to announcing a new opening date for the Red Line. However, we will complete the remaining milestones and ensure proper safety and operation of all systems prior to selecting a date to open the service to passengers. Safety has and will continue to be the top priority.
Milestones Completed Since May 13
• The Centralized Traffic Control (CTC) signal system is in full operation and Rail Dispatchers are utilizing it to direct train operations.
• The signal system, including new work added to the original scope of the project is complete and final crossings adjustments are underway.
• The installation of traffic signal preemption equipment at several crossings adjacent to intersections is complete and final adjustments are underway.
• All MetroRail, freight and Austin Steam Train engineers and supervisors are now certified on the use of the CTC signal system.
• MetroRail trains have begun operating under full-service conditions in the morning – to meet the timelines and stops according to the proposed service schedule but with no passengers aboard.
• MetroRail engineers have begun comprehensive contingency training to prepare and train for unforeseen challenges.
Remaining Milestones
• Complete adjustments to crossings and complete final testing for full-service operation.
• Complete full-service test runs to finalize schedules.
• Complete Engineer contingency training.
When will service begin?
Capital Metro will announce an opening date when the entire rail system is demonstrated to be operating in a consistent, reliable and safe manner. We will report back to the community in mid-July if not before.