Zilker Park “Great Lawn” Status

I thought this was interesting enough to post:

Zilker Park "Great Lawn" Status

On Saturday, October 3, 2009, rainy weather resulted in muddy conditions on the field when lower layer soil amendments percolated above the turf and covered the sod during the Austin City Limits event. 

Today the Parks and Recreation Department held the first post-event meeting with event organizers to discuss a more restrictive load out plan and preliminary remediation actions.  Concurrently, at the department's request, the organizers will begin immediate remediation steps supervised by the department. Contingent upon weather conditions, it is anticipated that reconditioning work will take an additional two weeks. It is anticipated that the lawn will begin to be opened by the end of October. The department expects to complete its initial turf condition assessment and complete remediation requirements also by the end of October. Event organizers will be performing and funding all the required work under department supervision as required in the event planning in the previous months

 

If you did not sign up to receive these newsletter, or would like to unsubcribe from receiving emails under this category, please click here to unsubscribe.

This entry was posted in Milwood News. Bookmark the permalink.